Projects & Studies: Water & Sewer
Information Related to Thompson Sewer Upgrades
Commencing in 2022, the Town of Thompson is upgrading two of its five municipally owned and -operated Wastewater Treatment Plants (WWTPs). For information on the upgrades for the Kiamesha Lake WWTP and the Emerald Green WWTP click on the link below.
Proposed Extension No. 07 of the Sackett Lake Sewer District – Tyler Wheat Property, SBL#59.-1-75.1, 59.1-75.2 & 59.-1-75.3 (Sackett Lake Road)
Proposed Extension No. 03 of the Consolidated Harris Sewer District – 190 Cold Spring Road (KA Annex LLC), SBL# 29.-1-21
- Consolidated-Harris-Sewer-District-Ext.3-for-KA-Annex-LLC-SBL29.-1-21-Res.-Auth.-Map-Plan-Report-10-21-2026.pdf
- Consolidated-Harris-Sewer-District-Ext.3-for-KA-Annex-LLC-SBL29.-1-21-Notice-ofAdoption-Auth.-Map-Plan-Report-10-21-2026.pdf
- Notice-of-Public-Hearing-Tues.-10-06-26-at-7PM-Consolidated-Harris-Sewer-District-Ext.3-for-KA-Annex-LLC-SBL29.-1-21.pdf
- Consolidated-Harris-Sewer-District-Map-Plan-Report-Ext.3-Dated-12-19-2025.pdf
- Consolidated-Harris-Sewer-District-Ext.-No.-3-Negative-Declaration-EAF.pdf
- Consolidated-Harris-Sewer-District-Ext.-No.-3-Res.-Making-Certain-Determinations.pdf
- Consolidated-Harris-Sewer-District-Ext.-No.-3-Res.-Preliminarily-Approving-Construction-of-Improvements.pdf
Notice of Public Hearing: Tuesday, 05/19/2026 at 7PM – Proposed Creation of the Rock Hill Emerald Springs Water District – Town of Thompson, SBL# 35.-1-9.6
Proposed Extension No. 05 of the Consolidated Kiamesha Sewer District – Evergreen Hills Estates LLC, SBL # 8.-1-2.1
Proposed Extension No. 04 of the Consolidated Harris Sewer District – 220 Cold Spring Road LLC & Cold Spring Road LLC (Prestige), SBL#’s 29.-1-22.1, 25.1, 24, 15, 34.1 & 45
Proposed Extension No. 5 of the Cold Spring Water District – 220 Cold Spring Road LLC & Cold Spring Road LLC (Prestige), SBL#’s 29.-1-22.1, 25.1, 24, 15, 34.1 & 45
Bonding on Consolidated Rock Hill/Emerald Green Sewer District Pump Station #6 & Collection System Project $4,900,000.00 (202-b)
- Order-Calling-Public-Hearing-09-02-2025-at-7PM-Consolidated-Rock-Hill-Emerald-Green-Sewer-District-Pump-Station-6-Collection-System-Project-Bonding-4900000.00-202-b.pdf
- Notice-of-Public-Hearing-09-02-2025-at-7PM-Consolidated-Rock-Hill-Emerald-Green-Sewer-District-Pump-Station-6-Collection-System-Project-Bonding-4900000.00-202-b.pdf
Proposed Extension No. 6 of the Sackett Lake Sewer District – Ari Jacobs, SBL# 56.-1-32.54
- Resolution to Order Map, Plan & Report - Adopted: 04/01/2025
- Notice of Adoption: Authorizing Preparation of a Map, Plan & Report for Proposed Extension No. 6 of the Sackett Lake Sewer District - Ari Jacobs, SBL# 56.-1-32.54
- Map, Plan & Report - Dated: 08/01/2025
- Resolution & Legal Notice to Schedule Public Hearing - 09-02-2025 at 7PM
- Final Order - 10/21/2025
Revised Bonding Sackett Lake Sewer District Collection System Improvement Project Increase to $2,264,000.00 (Increase of $100,064) – Project No. C3-5378-08-00
- Map, Plan & Report - Revised 02/19/2025
- Order Calling Public Hearing on 03-04-2025 at 7PM: Revised Bonding Increase for Sackett Lake Sewer District Collection System Improvement Project $2,264,000
- Notice of Public Hearing on 03-04-2025 at 7PM: Revised Bonding Increase for Sackett Lake Sewer District Collection System Improvement Project $2,264,000
- Public-Interest-Order-Bond-Increase-for-Sackett-Lake-Sewer-District-Collection-System-Improvement-Project-2264000.00-Increase-of-100064.00-Adopted-03-04-2025.pdf
- Bond-Resolution-Bond-Increase-for-Sackett-Lake-Sewer-District-Collection-System-Improvement-Project-2264000.00-Increase-of-100064.00-Adopted-03-04-2025.pdf
Proposed Extension No. 3 of the Consolidated Rock Hill-Emerald Green Sewer District – Catskill Veterinary Services, LLP, SBL #32.-1-14.1
Proposed Creation of the Rock Hill Emerald Springs Water District – Town of Thompson, SBL # 35.-1-9.6
- Resolution to Order Map, Plan & Report - Adopted: 12/17/2024
- Notice of Adoption Authorizing Preparation of a Map, Plan & Report for Proposed Formation of the Rock Hill-Emerald Springs Water District - SBL #35.-1-9.6
- Resolution & Legal Notice to Schedule a Public Hearing - 05-19-2026 at 7PM
- Proposed-Creation-of-Rock-Hill-Emerald-Springs-Water-District-Schedule-A-District-Property-Description.pdf
- Negative-Declaration-Resolution-Proposed-Creation-of-the-Rock-Hill-Emerald-Springs-Water-District-SBL-35.-1-9.6-Adopted-05-19-2026.pdf
- Resolution-Making-Certain-Determination-Proposed-Creation-of-the-Rock-Hill-Emerald-Springs-Water-District-SBL-35.-1-9.6-Adopted-05-19-2026.pdf
- Resolution-Preliminarily-Approving-Proposed-Creation-of-the-Rock-Hill-Emerald-Springs-Water-District-SBL-35.-1-9.6-Adopted-05-19-2026.pdf
- Final-Order-Creating-Rock-Hill-Emerald-Springs-Water-District-SBL-35.-1-9.6-Adopted-07-07-2026.pdf
Proposed Extension No. 2 of the Consolidated Harris Sewer District – Brookview Cottages, SBL #7.-1-44.2
- Resolution to Order Map, Plan & Report - Adopted: 10/15/2024
- Notice of Adoption Authorizing Preparation of a Map, Plan & Report for Proposed Extension No. 2 of the Consolidated Harris Sewer District - Brookview Cottages, SBL #7.-1-44.2
- Map, Plan & Report - Dated: April 01, 2025, Revised: April 29, 2025
- Public Hearing Notice - Tuesday, June 03, 2025 at 2PM
Proposed Ext. No. 4 of the Consolidated Kiamesha Sewer District – JK Expediting Services Corp., for Saddle Lane LLC, SBL#13.-3-36.1
- Resolution-to-Authorize-Map-Plan-Report-for-Proposed-Ext.-No.-4-of-the-Consolidated-Kiamesha-Sewer-District-in-the-Town-of-Thompson-08-20-2024.pdf
- Legal-Notice-of-Adoption-to-Authorize-Map-Plan-Report-for-Proposed-Ext.-No.-4-of-the-Consolidated-Kiamesha-Sewer-District-in-the-Town-of-Thompson-08-20-2024.pdf
- Map-Plan-Report-Consolidated-Kiamesha-Sewer-Dist-Ext04-for-Saddle-Lane-LLC-SBL13.-3-36.1-Dated-08-05-2025.pdf
- Notice-of-Public-Hearing-Tues.-05-05-26-at-7PM-Consolidated-Kiamesha-Sewer-Dist-Ext.-04-for-Saddle-Lane-LLC-SBL13.-3-36.1.pdf
- Schedule-A-Revised-Property-Description-of-District-Extension-04-07-2026.pdf
- Negative-Declaration-Resolution-Consolidated-Kiamesha-Sewer-Dist-Ext04-for-Saddle-Lane-LLC-SBL13.-3-36.1-05-05-2026.pdf
- Resolution-Making-Certain-Determinations-in-Relation-to-Consolidated-Kiamesha-Sewer-Dist-Ext04-for-Saddle-Lane-LLC-SBL13.-3-36.1-05-05-2026.pdf
- Resolution-Preliminarily-Approving-Consolidated-Kiamesha-Sewer-Dist-Ext04-for-Saddle-Lane-LLC-SBL13.-3-36.1-05-05-2026.pdf
- Final-Order-Expanding-Consolidated-Kiamesha-Sewer-Dist-Ext-4-for-Saddle-Lane-LLC-SBL13.-3-36.1-Adopted-07-07-26.pdf
Revised Bonding Consolidated Rock Hill/Emerald Green Sewer District Waste Water Treatment Plant Upgrade Project $16,057,378
- Map, Plan & Report - Revised 01/24/2024
- Resolution ReAffirming Negative Declaration Under SEQR
- Order-Calling-Public-Hearing-on-03-05-24-@-7PM-Revised-Bonding-Consolidated-Rock-HillEmerald-Green-Sewer-District-WWTP-Upgrade-Project-16057378.pdf
- Notice-of-Public-Hearing-on-03-05-24-@-7PM-Revised-Bonding-Consolidated-Rock-HillEmerald-Green-Sewer-District-WWTP-Upgrade-Project-16057378.pdf
- Public-Interest-Order-Revised-Bonding-Consolidated-Rock-Hill-Emerald-Green-Sewer-District-WWTP-Upgrade-Project-16057378-Adoped-03-05-2024.pdf
- Bond-Resolution-Revised-Bonding-Consolidated-Rock-Hill-Emerald-Green-Sewer-District-WWTP-Upgrade-Project-16057378-Adopted-03-05-2024.pdf
- Legal-Notice-of-Estoppel-Revised-Bonding-Consolidated-Rock-Hill-Emerald-Green-Sewer-District-WWTP-Upgrade-Project-16057378-Adopted-03-05-2024.pdf
Revised Bonding for Consolidated Kiamesha Sewer District Waste Water Treatment Plant Upgrade Project $34,792,360
- Map, Plan & Report - Revised 01/23/2024
- Resolution ReAffirming Negative Declaration Under SEQR
- Order-Calling-Public-Hearing-on-03-05-24-@-7PM-Revised-Bonding-for-Consolidated-Kiamesha-Sewer-District-WWTP-Upgrade-Project-34792360.pdf
- Notice-of-Public-Hearing-on-03-05-24-@-7PM-Revised-Bonding-for-Consolidated-Kiamesha-Sewer-District-WWTP-Upgrade-Project-34792360.pdf
- Public-Interest-Order-Revised-Bonding-for-Consolidated-Kiamesha-Sewer-District-WWTP-Upgrade-Project-34792360-Adopted-03-05-2024.pdf
- Bond-Resolution-Revised-Bonding-for-Consolidated-Kiamesha-Sewer-District-WWTP-Upgrade-Project-34792360-Adopted-03-05-2024.pdf
- Legal-Notice-of-Estoppel-Revised-Bonding-for-Consolidated-Kiamesha-Sewer-District-WWTP-Upgrade-Project-34792360-Adopted-03-05-2024.pdf
Melody Lake Water District Increasing the Maximum Amount to be Expended from $725,000 to $1,250,000
- Map, Plan & Report for Proposed Well House Project in Melody Lake Water District - Revised 09-12-2023
- Order-Calling-Public-Hearing-Increase-Improvement-of-Facilities-for-Melody-Lake-Water-District-1250000-Bonding.pdf
- Public Interest Order to Increase Estimated Maximum Cost to $1,250,000
- Bond Resolution to Increase Estimated Maximum Cost to $1,250,000
- Legal Notice of Estoppel to Increase Estimated Maximum Cost to $1,250,000
- Legal Notice of Estoppel to Increase Maximum Cost to $1,357,708.42
Proposed Extension No. 3 of Consolidated Kiamesha Sewer District – JK Expediting Services Corp., SBL#’S 9.-1-8.2, 61.-1-11.1, 11.3, 11.4, 11.5 & 11.6
- Notice-of-Public-Hearing-07-05-2023-at-7PM-Proposed-Extension-No.-3-of-the-Consolidated-Kiamesha-Sewer-District-6-Parcels.pdf
- Revised Map, Plan and Report - Dated: 06-20-2023
- Negative Declaration Under SEQR
- Resolution Making Certain Determinations in Relation to Proposed Extension
- Resolution Preliminarily Approving Extension and Construction of Improvements
- Final Order Expanding Consolidated Kiamesha Sewer District, Adopted: 11-21-2023
FORMATION/CREATION OF PROPOSED MONTICELLO MOTOR CLUB SEWER DISTRICT TO INCLUDE (11) TOWN OF THOMPSON TAX PARCELS
Consolidated Rock Hill-Emerald Green Sewer District Pump Station #1, #2 & #3 Improvements Project Bonding 202b Additional $987,800 Bonds, Total of $3,279,000 on 04-04-2023 at 7PM
- Order-Calling-Public-Hearing-Consolidated-Rock-Hill-Emerald-Green-Sewer-District-Bonding-Additional-987800-Bonds-Total-of-3279000-on-04-04-2023-at-7PM.pdf
- Public-Interest-Order-Consolidated-Rock-Hill-Emerald-Green-Sewer-District-Revised-Bonding-Additional-987800.00-Total-3279000.00.pdf
- Bond-Resolution-Consolidated-Rock-Hill-Emerald-Green-Sewer-District-Revised-Bonding-Additional-987800.00-Total-3279000.00.pdf
- Legal-Notice-of-Estoppel-Consolidated-Rock-Hill-Emerald-Green-Sewer-District-Revised-Bonding-Additional-987800.00-Total-3279000.00.pdf
Sackett Lake Sewer District Collection System Improvement Project Bonding – 202b Rehabilitation & Replacement of Sewer Main Additional $570,642.70 Bonds, Total of $2,163,936
- Order-Calling-Public-Hearing-Sackett-Lake-Sewer-District-Bonding-Additional-570649.70-Bonds-Total-of-2163936-on-04-04-2023-at-7PM.pdf
- Public-Interest-Order-Sackett-Lake-Sewer-District-Collection-System-Improvements-Project-Revised-Bonding-Additional-570642.70-Total-2163936.00.pdf
- Bond-Resolution-Sackett-Lake-Sewer-District-Collection-System-Improvements-Project-Revised-Bonding-Additional-570642.70-Total-2163936.00.pdf
- Legal-Notice-of-Estoppel-Sackett-Lake-Sewer-District-Collection-System-Improvements-Project-Revised-Bonding-Additional-570642.70-Total-2163936.00.pdf